A - Preparatory Actions
Preparatory actions are preliminary activities necessary to realize conservative actions (C actions):
- A.1 – Authorizations and Agreements
- A.2 – Surveys and modelling simulations
- A.3 – Planning of hydraulic works
- A.4 – Planning of morphological works
- A.5 – Stakeholder sharing
Project plans of hydraulic (A.3 action) and morphological (A.4 action) works will be submitted to the examination of Authorities to obtain regular and formal authorizations (A.1 action).
Technical details, strictly connected with planning, will be defined according to data collection, results of surveys and modelling activities (A.2 action).
Preparatory actions also include specific training courses and meeting with stakeholders (A.5 action).